Procurement Bill to mandate prompt payment
The Cabinet Office leads on how the Government spends some £300bn of public funds annually. It is currently navigating the post-Brexit Procurement Bill – which will shape how the public sector buys goods, services and works - through Parliament, on the way to it becoming law.
ECA’s Rob Driscoll Chairs the Cabinet Office Payment Advisory Group. This Group has been raising high level awareness that, while current UK enactment of EU law states tiers 1, 2 and 3 should be paid in 30 days under public sector contracts, there has been no reliable way of knowing if this really happens. However, following a meeting with Ministers Baroness Neville-Rolfe and Brendan Clarke-Smith MP this month, Rob Driscoll advises that the forthcoming Bill now includes provisions to establish 30-day payment within the public sector by:
- ensuring 30-day payment will be a mandatory implied term into tier 1, 2 and 3 construction contracts – overriding any other payment terms within relevant contracts (widely regarded as a milestone achievement); and
- requiring public sector procurers to report on their payment performance in the same way as the private sector.
Should the new provisions be enacted as currently proposed, non-compliance would then be dealt with by the Public Procurement Review Service, supported by the Small Business Commissioner.
This article first appeared on the ECA news and blog site under the same title dated October 14, 2022.
--ECA
[edit] Related articles on Designing Buildings
- Connected procurement.
- Difference between procurement and purchasing.
- European Single Procurement Document ESPD.
- Maintenance Repair Operations MRO.
- Procurement policy.
- Procurement route – frequently asked questions.
- Procurement strategy.
- Public procurement.
- Renovate, operate, transfer (ROT).
- Subcontract procurement.
- Transforming Public Procurement Green Paper.
- Two-stage tender.
- What is the most common procurement route?
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.